Film crew in Flint today to tape service line replacement FLINT, Mich. — Mayor Karen Weaver’s FAST Start initiative to replace all the lead-tainted service
Film crew in Flint today to tape service line replacement FLINT, Mich. — Mayor Karen Weaver’s FAST Start initiative to replace all the lead-tainted service
FLINT, Mich. — The City of Flint is accepting bids to replace lead-tainted service lines leading to 6,000 homes in 2017, allowing Mayor Karen Weaver
December 19, 2016 (FLINT, Mich) — Lead-tainted service lines at 625 homes have been replaced so far as part of Mayor Karen Weaver’s ongoing FAST
The Water Infrastructure Improvements for the Nation Act authorizes funding for Flint and other communities that was appropriated as part of the government funding bill
December 1, 2016 (FLINT, Mich) — Mayor Karen Weaver announced today that a study by University of Michigan professors working with leaders of her FAST
November 21, 2016 (FLINT, Mich) —Lead-tainted service lines at 460 homes have been replaced so far as part of Mayor Karen Weaver’s FAST Start initiative,
FLINT, Mich. — Lead-tainted service lines at 346 homes have been replaced so far as part of Mayor Karen Weaver’s FAST Start initiative, with 51
November 7, 2016 (FLINT, Mich) — Lead-tainted service lines at 295 homes have been replaced so far as part of Mayor Karen Weaver’s FAST Start
November 1, 2016 (FLINT, Mich) — Crews began work on Phase 3 of Mayor Karen Weaver’s FAST Start initiative this week with the goal of
October 31, 2016 (FLINT, Mich.) ― Mayor Karen Weaver today kicked off the third phase of her FAST Start initiative by announcing the neighborhoods where
October 24, 2016 (FLINT, Mich) — Volunteers from AARP Michigan will be going door-to-door in some Flint neighborhoods today to help residents complete consent forms for the next phase
October 18, 2016 (FLINT, Mich) — The second phase of Mayor Karen Weaver’s FAST Start initiative wrapped up today, with crews replacing lead-tainted service lines
October 10, 2016 (FLINT, Mich) — Lead-tainted service lines at 192 homes have been replaced so far as part of Mayor Karen Weaver’s FAST Start
October, 3, 2016 (Flint, Mich) — Lead-tainted service lines have been replaced at 163 Flint homes over the last month as part of Mayor Karen
FLINT, Mich. — Lead-tainted service lines at 144 homes have been replaced so far as part of the second phase of Mayor Karen Weaver’s FAST
September 19, 2016 (FLINT) — Lead-tainted service lines at 93 homes have been replaced so far as part of Mayor Karen Weaver’s FAST Start initiative,
September 9, 2016 (FLINT, Mich) ― It has been a productive second week of work since the second phase of the FAST Start initiative got
September 7, 2016 (Flint, Mich) — Crews from three area companies are now on the job replacing lead-tainted pipes at homes in the City of Flint.
August 31, 2016 (Flint, Mich)– Construction crews were out early today as they resumed digging and replacing lead-tainted pipes at homes in the City of Flint
May 31, 2016 (Flint) — Mayor Karen Weaver and the City of Flint have completed a significant step in the effort to move forward with